COLUMBIA, S.C. (AP) — The parent company of South Carolina Electric & Gas Co. is offering the site of a failed nuclear reactor project to the state-owned utility Santee Cooper.

SCANA has proposed giving the VC Summer nuclear power plant site in Fairfield County to Santee Cooper so the project could be preserved and perhaps finished at some point in the future, The State newspaper reported.

SCE&G and Santee Cooper abandoned their joint effort July 31 after spending more than $9 billion, both blaming the failure on the bankruptcy by principal contractor Westinghouse. SCE&G customers have been charged nearly $2 billion toward interest on the company's debt, via a series of rate hikes since 2009, without any power being generated.

That amounts to about $27 per month for each ratepayer, charges that continue despite the project's failure. SCE&G has proposed reducing that cost by about $5 a month, but that would have to be approved by state regulators.

SCANA's proposal was contained in a Dec. 4 letter obtained by the newspaper.

The newspaper reported in Sunday's edition that choosing not to preserve the site is part of SCANA's strategy to show the Internal Revenue Service it has abandoned the effort and deserves a $2 billion tax write-off.

SCANA could decide later this week to surrender the federal license for the project. Giving up the operating license would be another way to show the utility should be eligible for the tax write-off.

Getting the tax write-off would help pay down the nearly $5 billion in construction costs that SCANA has paid for the project.

SCANA owns 55 percent of the project and Santee Cooper owns 45 percent. The two utilities operate an existing reactor at the site that was completed more than 30 years ago. That operation is not affected by the discussions about how to handle the failed expansion project.

Santee Cooper already owes about $4 billion for the failed project.

The state-owned utility said it doesn't know how much it would cost to protect valuable components for the abandoned Units 2 and 3, hire security staff and pay workers to occasionally operate machinery that might otherwise rust over.

Sponsored by

Get All the Electric Light & Power and POWERGRID International to Your Inbox

Subscribe to Electric Light & Power or POWERGRID International and the email newsletter today at no cost and receive the latest news and information.

Related Articles

Ohio nuclear power plants could get financial bailout

04/15/2019

Backers of the plan said it would generate $300 million each year for clean energy production, but they also think it shou...

Japan's PM visits Fukushima nuclear plant in revival message

04/15/2019

The visit by Abe, who last went to the Fukushima Dai-ichi plant five years ago, was seen as damage control after Yoshitaka...

Minnesota gov. says clean energy means jobs

04/10/2019

"We are outpacing other states," the governor said. "Now is the time for Minnesota to seize the momentum.&q...

Debates over nuclear bailout comes to Pennsylvania House

04/09/2019

The legislation is opposed by oil and gas trade associations, the AARP and the Pennsylvania Chamber of Business and Indust...