The Tennessee Valley Authority has identified preferred locations for electric transmission upgrades that would reduce power outages and improve reliability in the Rugby-Sunbright area of eastern Tennessee.

A new substation and power line will provide additional power supply for Plateau Electric Cooperative’s service area to support future increased loads, reduce outages and improve backup power supply.

As proposed by the No. 1 alternative, TVA would build the Rugby Substation and connect it to the Livingston-Huntsville 161 kV transmission line. TVA would also build 7.25 miles of power line from the new Rugby Substation to Plateau Electric’s existing Sunbright Substation.

The selected route is expected to have the least impact on the area, based on public input from an open house in April 2014, and additional evaluation of other factors, including social, environmental and engineering impacts. A National Environmental Policy Act review is also pending.

TVA will meet with property owners along the proposed right-of-way to obtain easements for construction, operation and maintenance of the line. The project will require a new right of way. Property owners would still own the property and be compensated for the easements at fair market value.

TVA is expected to begin surveys this spring and start acquiring easements in spring 2016. Construction is scheduled to begin in spring 2017 on the substation and in summer 2017 on the power line with the project scheduled to be completed by fall 2018.

The Tennessee Valley Authority is a corporate agency of the U.S. that provides electricity for business customers and local power companies serving nine million people in parts of seven southeastern states. TVA receives no taxpayer funding, deriving virtually all of its revenues from sales of electricity.

In addition to operating and investing its revenues in its electric system, TVA provides flood control, navigation and land management for the Tennessee River system and assists local power companies and state and local governments with economic development and job creation.

Sponsored by

Get All the Electric Light & Power and POWERGRID International to Your Inbox

Subscribe to Electric Light & Power or POWERGRID International and the email newsletter today at no cost and receive the latest news and information.

Related Articles

NRECA, SEPA launch new regulatory innovation initiative

03/18/2019

The initiative’s vision is to enable the evolution of state regulatory processes and practices in order to address the sca...

EnerNex modernize Public Utilities Commission of Ohio power grid

03/14/2019

These two workgroups will address specific tasks articulated in the PowerForward Roadmap and will build upon the collabora...

NYPA grid lab studies how to integrate renewables onto transmission grid

03/13/2019

The New York Power Authority’s new Advanced Grid Innovation Laboratory for Energy is driving cost reductions and operation...

Judge eases wildfire plan for Pacific Gas and Electric

03/07/2019

Judge William Alsup said in an order late Tuesday that he's now considering making PG&E comply with targets in a wildf...