N.C. regulators approve Duke Energy's request to build 3 solar facilities

Sponsored by

Duke Energy won regulatory approval from the North Carolina Utilities Commission (NCUC) to acquire and construct three large solar power facilities in eastern North Carolina.

The three projects are part of Duke Energy's $500-million solar expansion announced in September, which also includes buying power under purchase power agreements from five other new solar power projects in both the Duke Energy Carolinas and Duke Energy Progress service territories.

Located in Bladen, Duplin and Wilson counties, the three sites owned by Duke Energy will provide energy and renewable energy certificates to benefit Duke Energy customers as cost-effective components of the company's portfolio to comply with the N.C. Renewable Energy Portfolio Standard.

The projects will begin construction in early 2015, and are expected to be completed by the end of 2015. More than 750 construction jobs are expected during the peak of construction at the three sites.

The three projects will total 128 MW of capacity. Overall, Duke Energy's expansion totals 278 MW of new solar capacity. The company's efforts have contributed to North Carolina's status as fourth in the nation for installed solar power.

The three acquired projects include:

·      The 65 MW Warsaw Solar Facility in Duplin County. The Certificate of Public Convenience and Necessity (CPCN) was transferred to Duke Energy from Strata Solar.

·      The 40 MW Elm City Solar Facility in Wilson County. The CPCN was transferred to Duke Energy from HelioSage Energy.

·      The 23 MW Fayetteville Solar Facility in Bladen County, near the Cumberland County border. The CPCN was transferred to Duke Energy from Tangent Energy Solutions.

Sponsored by

Get All the Electric Light & Power and POWERGRID International to Your Inbox

Subscribe to Electric Light & Power or POWERGRID International and the email newsletter today at no cost and receive the latest news and information.

Related Articles

Top 10 solar power states

Top 10 solar power states

07/17/2017

NTE Energy wins approval for new solar power array

06/26/2017

The issuance of the CPCN, a requirement for beginning construction, is a crucial step for the 30 MW project

Solar plant to provide 80 percent of Ohio school's power

06/21/2017

An Ohio school hopes to generate 80 percent of its electricity through a new solar power plant

Finally - A Market-Based, Investable Approach to Energy Efficiency

06/19/2017 It's all about creating sustained, predictable cash flows. It's easy for the solar and wind energy industries: they instal...