J.P. Morgan, First Wind strike wind farm agreement

Sponsored by

Investors advised by J.P. Morgan Asset Management made a majority investment in two of First Wind’s projects. The investments include the Palouse Wind project in Washington and the Route 66 wind power project in Texas, which is currently under construction. First Wind will operate and manage both projects as the company continues to expand its third-party operations group.

The Palouse Wind project features 58 Vestas V100-1.8 MW wind turbines located near the town of Oakesdale, Washington. The project achieved commercial operations in December 2012, and the wind power from the project interconnects to the Avista 230kV Benewah-to-Shawnee transmission line.

Palouse Wind harnesses enough wind to generate up to 105 MW for Whitman County and much of the Northwest—enough to provide power for the equivalent of as many as 30,000 homes in Eastern Washington. The energy company Avista is purchasing the power and delivering it to homes and businesses in the region.

Route 66 is a 150 MW wind project under construction in Armstrong and Carson Counties near Amarillo, Texas. Construction began in late 2013 and is slated to be completed in 2015. Once complete, the project will be comprised of 75 Vestas V110 turbines with a capacity of 2 MW each that will deliver clean energy to the ERCOT (Electric Reliability Council of Texas) power markets through the new CREZ (Competitive Renewable Energy Zone) transmission system. The project is expected to power about 49,000 Texas homes annually.

Sponsored by

Get All the Electric Light & Power and POWERGRID International to Your Inbox

Subscribe to Electric Light & Power or POWERGRID International and the email newsletter today at no cost and receive the latest news and information.

Related Articles

Developer to shrink Oregon wind energy project

The Oregon Department of Energy said Friday it will take public comments on the proposal until Sept. 19 

Consumers Energy to start work early on wind turbine project

06/19/2017

The initial Cross Winds Energy Park in Tuscola County started serving electric customers in Michigan's Thumb region in 2014

Alaska becomes microgrid testing ground

06/19/2017

Alaska has become a testing ground for sustainable technologies that the rest of the world is increasingly interested in u...

After years of false starts, Massachusetts offshore wind market heats up

06/13/2017

Massachusetts' bid to become the nation's leader in offshore wind power is ramping up