The U.S. Environmental Protection Agency is out for public comment until Oct. 17 on a draft air permit for the Red Gate power plant project of South Texas Electric Cooperative (STEC).

The cooperative in January 2013 applied at EPA’s Region 6 office for a greenhouse gas permit under the prevention of significant deterioration (PSD) program for the Red Gate Power Plant project, according to GenerationHub.

The proposed plant plant construction will occur in Hidalgo County at 3428 West FM 490, at Edinburg, Texas. The site is located on undeveloped land in Edinburg, about 2.5 miles west of Texas State Highway 281, with Farm-to-Market Road 490 forming the northern border.

In connection with the same proposed project, STEC submitted a PSD permit application for non-GHG pollutants to the Texas Commission on Environmental Quality (TCEQ) in October 2012, which was issued in December 2013.

STEC proposes to construct a new 225 MW (nominal) electric power plant, consisting of twelve Wartsila natural gas-fired engines (Model 18V50SG) and associated equipment including a firewater pump engine, circuit breakers and a diesel-fired emergency generator.

“STEC’s application explains that its system experienced strong growth in 2011 as a result of extreme weather conditions in both the summer and winter months, such that sales to member cooperatives increased 11.78 percent to 5,014,032 MW hours,” EPA noted. “STEC asserts that system peak load was 1242 MW, up over 10 percent from the 1127 MW peak load realized in 2010 and that strong system growth is expected to continue with a projected 219 MW capacity additions required to serve the STEC member load by 2017.”

To respond to this growth, STEC has proposed the Red Gate Power Plant. The Wartsila 18V50SG is a nominal 18.76 MW, four-stroke, spark-ignition, lean burn reciprocating internal combustion engine (SI RICE).

“The engines will be used to provide renewable support, transmission grid support, energy and ancillary services to meet its eight member distribution cooperatives’ energy and capacity needs as well as to support the Energy Reliability Council of Texas (ERCOT) grid,” EPA said.

Sponsored by

Get All the Electric Light & Power and POWERGRID International to Your Inbox

Subscribe to Electric Light & Power or POWERGRID International and the email newsletter today at no cost and receive the latest news and information.

Related Articles

U.S. solar market tops 10 GW in 2018, again

03/14/2019 For the third year in a row, the U.S. solar industry installed double-digit gigawatts (GW) of solar PV capacity, with 10.6...

FERC issues preliminary permit to study 1,200-MW Southeast Oklahoma Pumped Storage project

03/04/2019

The Federal Energy Regulatory Commission has issued a preliminary permit to Southeast Oklahoma Power Corporation to study ...

Residential PV + batteries as wholesale energy market suppliers are just the ‘tip of the spear’

02/19/2019 Last week, Sunrun announced that its bid to supply 20 MW of residential solar + storage capacity into the New England ISO ...

Be careful when relying on insurance coverage to contain utilities’ wildfire risks

02/19/2019 The recent wildfires in California have been devastating to life and property. Plaintiffs that lost property are attributi...