Duke Energy responds to change in dam condition, notice of violation at retired Cape Fear Plant

Sponsored by

Duke Energy notified the North Carolina Department of Environment and Natural Resources (NCDENR) and other state and local officials that a gap has developed on the inside embankment of one of the Cape Fear ash basins.

The basin dam remains safe and structurally sound, Duke reported.

A small depression was observed two weeks ago on the embankment of the basin, which was constructed in 1985. Site personnel have been monitoring it, and it has not changed in size or condition since it was discovered.

Company officials observed on Thursday, March 20, however, that the depression had developed into a narrow gap about 35 feet long and three to four inches wide.

Company engineers and engineering consultants responded to the site immediately to make repairs. No ash basin discharge has occurred, and out of an abundance of caution, the company is taking steps to prevent any potential for discharge.

NCDENR issued a Notice of Violation today related to Duke Energy's actions to lower basin levels to perform maintenance work on the 1985 and 1978 ash basins.

The company had identified through routine inspections that maintenance was needed on the risers, the vertical pipes that transfer basin water to the permitted discharge system.

The water was being pumped to the existing, permitted outfalls and was being monitored according to the plant permit. Duke Energy notified the agency prior to beginning work and will respond to the agency within the 30 days as requested.

The Cape Fear Plant retired in 2012, and no ash has been produced since that time.

Sponsored by

Get All the Electric Light & Power and POWERGRID International to Your Inbox

Subscribe to Electric Light & Power or POWERGRID International and the email newsletter today at no cost and receive the latest news and information.

Related Articles

Neil Chatterjee sworn in as FERC commissioner

08/08/2017

Commissioner Neil Chatterjee was sworn in Tuesday to his new position at the Federal Energy Regulatory Commission

Tocardo gets Ofgem support for tidal power project in Scotland

06/26/2017

Tocardo Tidal Power said Ofgem has granted accreditation under the renewables obligation plan for Tocardo’s 1.4 MW deploym...

Alaska becomes microgrid testing ground

06/19/2017

Alaska has become a testing ground for sustainable technologies that the rest of the world is increasingly interested in u...

Case Study: Georgia Power Uses Traveling Wave Fault Location to Find Transmission Line Fault

05/01/2017 Faults on electric power grids are never good, but sometimes are unavoidable due to inclement weather or other unforeseen ...