DTE Energy Services Inc. (DTEES) has finished its construction project to convert a shuttered coal-fired power plant at the Port of Stockton to operate on biomass fuel.

The plant, known as Stockton Biomass, began commercial operations on February 21. It is selling its renewable power to Pacific Gas & Electric (PG&E) to help it meet its renewable energy requirement.

The plant will use about 320,000 tons of woody biomass fuel annually to generate about 45 MW of renewable power — enough electricity to meet the needs of 45,000 homes. The fuel primarily is derived from urban wood waste, tree trimmings and agricultural processes.

The site, once one of the most polluted in San Joaquin Valley, now is home to one of the cleanest solid-fuel power plants in the country. It is providing 35 high-quality jobs and another 100 indirectly involved with DTE Stockton's fuel supply infrastructure.

The plant began operation in 1989 as a coal-fired power plant and ceased operation in April 2009.  DTEES purchased it in June 2010 with plans to convert the plant to biomass. At its peak, the construction project employed about 100 workers. DTEES replaced the boilers and employed the best available control technologies to minimize air emissions.

DTEES, a unit of DTE Energy, is headquartered in Ann Arbor, Mich. It has completed similar biomass conversions in Cassville, Wis. and Bakersfield, Calif. The company also operates biomass power plants in Woodland, Calif. and Mobile, Ala. An official ribbon-cutting for the Stockton plant will be held later this spring.

Sponsored by

Get All the Electric Light & Power and POWERGRID International to Your Inbox

Subscribe to Electric Light & Power or POWERGRID International and the email newsletter today at no cost and receive the latest news and information.

Related Articles

Developer to shrink Oregon wind energy project

The Oregon Department of Energy said Friday it will take public comments on the proposal until Sept. 19 

Tocardo gets Ofgem support for tidal power project in Scotland

06/26/2017

Tocardo Tidal Power said Ofgem has granted accreditation under the renewables obligation plan for Tocardo’s 1.4 MW deploym...

NTE Energy wins approval for new solar power array

06/26/2017

The issuance of the CPCN, a requirement for beginning construction, is a crucial step for the 30 MW project

ABB to power Aruba with microgrid; enable more renewable energy

06/22/2017

ABB microgrid will integrate wind and solar energy to provide electricity to Caribbean island that was previously fully de...