JCP&L substation in Tewksbury improves electric service

Sponsored by

Jersey Central Power & Light's (JCP&L) new $7.3 million substation in Tewksbury is in service, providing greater redundancy to the local electric system and improved service reliability to customers.

The substation converts high voltage from transmission lines to lower voltages that are used to serve businesses and residents in the Tewksbury area.

The new substation automatically switches customers to another circuit when an outage occurs, restoring service sooner. While customers in Tewksbury primarily benefit from this project, the new facility helps support customers in portions of Hunterdon, Morris and Somerset counties as well.

Since 2001, JCP&L has invested more than $2 billion in capital improvements to its distribution system.

Sponsored by

Get All the Electric Light & Power and POWERGRID International to Your Inbox

Subscribe to Electric Light & Power or POWERGRID International and the email newsletter today at no cost and receive the latest news and information.

Related Articles

NRECA, SEPA launch new regulatory innovation initiative

03/18/2019

The initiative’s vision is to enable the evolution of state regulatory processes and practices in order to address the sca...

EnerNex modernize Public Utilities Commission of Ohio power grid

03/14/2019

These two workgroups will address specific tasks articulated in the PowerForward Roadmap and will build upon the collabora...

NYPA grid lab studies how to integrate renewables onto transmission grid

03/13/2019

The New York Power Authority’s new Advanced Grid Innovation Laboratory for Energy is driving cost reductions and operation...

Judge eases wildfire plan for Pacific Gas and Electric

03/07/2019

Judge William Alsup said in an order late Tuesday that he's now considering making PG&E comply with targets in a wildf...