B&W to retrofit Wisconsin coal-fired unit

Sponsored by

Charlotte, N.C., April 30, 2012 — The Babcock & Wilcox Power Generation Group, Inc. won a contract worth about $150 million to design, supply and erect environmental equipment for Alliant Energy unit Wisconsin Power and Light Co.'s coal-fired Columbia Energy Center in Pardeeville, Wis.

B&W PGG will engineer and supply four spray dry absorber systems, two pulse jet fabric filters, a lime preparation system, ash recycle systems and related equipment for Columbia Units 1 and 2. B&W PGG's unit, Babcock & Wilcox Construction Co., Inc. will erect and install the environmental equipment.

Engineering work for the project is currently underway, with construction to begin in October 2012.

Sponsored by

Get All the Electric Light & Power and POWERGRID International to Your Inbox

Subscribe to Electric Light & Power or POWERGRID International and the email newsletter today at no cost and receive the latest news and information.

Related Articles

North Carolina solar power jumps to No. 2, Duke Energy continues investment

03/15/2019

With 4 million customers in North Carolina and South Carolina, Duke Energy continues to build a smarter energy future

New Mexico Supreme Court delays power plant closing

03/04/2019

The utility was facing a deadline to turn in its application for abandoning the San Juan Generating Station near Farmington

Alabama Power: Closing coal plant will cost customers

03/04/2019

The plant is located in Walker County near Parrish

Demolition date set for closed Massachusetts coal plant

03/01/2019

Commercial Development plans to turn the former plant into a multiuse site mainly dedicated to supporting off-shore wind f...