PP&L will begin construction of a selective catalytic reduction system in November at its two coal-fueled units at the Montour plant near Washingtonville, Penn. Plans call for the SCRs (contracted to DB Riley) to be in service by May 2000 on Unit 2 and by May 2001 on Unit 1. PP&L is also installing two new replacement electrostatic precipitators (contracted to Wheelabrator Air Pollution Control Inc.).