California ISO revises draft 2013-2014 transmission plan

Sponsored by

The California Independent System Operator (Cal-ISO) released a revised draft of its 2013-2014 transmission plan on March 12, identifying 28 transmission projects representing $1.7bn of transmission projects needed to maintain system reliability.

The original draft plan, released on Feb. 3, identified 29 projects representing an estimated $1.83bn of investment.

The revised draft removed the inclusion of the Henrietta 230-kV breaker project, which the ISO said it would assess further in the 2014-2015 transmission planning cycle, a spokesperson for Cal-ISO told TransmissionHub.

“In addition to the removal of the Henrietta 230-kV breaker project, the estimated cost of the Mesa Loop-in project was reduced, which resulted in the change in the costs from $1.83bn to 1.7bn,” the spokesperson said.

The Mesa Loop-in project, which involves looping the Vincent-Mira Loma 500-kV transmission line into the existing Mesa substation and upgrading the substation to include a 500-kV bus, is estimated to cost $464m to $614m.

The revised plan had also identified an increased number of projects eligible for competitive solicitation, or seven, compared to the five identified in the original plan. The ISO had identified six projects eligible for competitive solicitation as of its March 6 stakeholder meeting. The competitive solicitation process will open in April.

The seven projects are:

·      The Delaney-Colorado River 500-kV transmission line, which is estimated to cost between $469m and $560m. The project, proposed by Arizona Public Service Co., is 110 miles long and would run from Arizona to California.

·      The Imperial Valley flow controller, which involves installing a phase shifter or back-to-back HVDC flow control device on path to CFE.

·      The Estrella 230/70-kV substation, which involves building the new 230/70-kV Estrella substation, approximately 5 miles east of the existing Paso Robles substation. The Estrella 230-kV bus will be looped into the Morro Bay-Gates 230-kV line. A new 230/70-kV transformer will be installed at the Estrella substation. In addition, a 45 MVA distribution transformer will be installed on the Estrella 230-kV bus. The Estrella 70-kV bus will be looped into the existing San Miguel-Paso Robles 70-kV line. A reverse power relay will be installed on the Estrella 230/70-kV and the existing Templeton 230/70-kV #1 transformer banks to prevent the 70-kV system from feeding the 230-kV system. The estimated cost of the project with a single loop into the existing Morro Bay-Gates 230-kV Line is $35m to $45m, and the proposed in-service date is May 2019.

·      The Wheeler Ridge Junction 230/115-kV substation, which involves building a new 230/115-kV substation at Wheeler Ridge Junction and converting the existing Wheeler Ridge-Lamont 115-kV to 230-kV operation.

·      The Spring 230/115-kV substation near Morgan Hill.

·      The Miguel 500-kV voltage support, which involves installing up to 375 MVAR of reactive support at the Miguel substation to mitigate low voltage conditions at Miguel and ECO 500-kV buses under normal summer peak load conditions. The estimated cost of the project is about $30m to $40m, and the proposed in-service date is June 1, 2017.

·      The Suncrest SVC, which entails a 300 MVAr static VAR compensator (SVC) at the Suncrest 230-kV bus, estimated to cost $65m and scheduled to come online in 2017.

Comments on the draft are due by 11:59 p.m. on March 13.

SCE is a subsidiary of Edison International (NYSE:EIX).

Sponsored by

CURRENT ARTICLES

IIT, ComEd, Silver Spring and West Monroe Partners open smart grid center

09/23/2014 The center together academic, industry and utility experts to provide a fully-functional test environment for smart grid a...

Brazil adds 74 power generation projects to power auction

09/23/2014 Brazil's mining and energy ministry (MME) has added 74 power generation projects to its A-5 power auction catalog 

HelioSage sells 40 MW solar power project to Duke Energy

09/23/2014

HelioSage Energy has announced the sale of a 40 MW AC solar photovoltaic project to Duke Energy 

Senate resolution opposes Canadian nuclear waste plan

09/23/2014 A federal panel in Canada is taking testimony on the plan to store low- and intermediate-level waste from nuclear power pl...

JCP&L upgrades enhance reliability on circuits in New Jersey

09/23/2014

The work is part of the company's effort to use advanced technology to help enhance service reliability to customers

Energy security is a challenge in Brazil for the next years

09/23/2014 Discussions about Energy Security that might define the course of the electric power sector in the country will take place...

Vietnam's EVN HCMC, Trilliant sign smart grid contract

09/23/2014 Smart grid firm Trilliant signed a contract with EVN HCMC, a unit of EVN, the largest power company in Vietnam, for a smar...

ON DEMAND WEBCASTS

3D BIM for Substations—Driving Efficiency from Design Through Operation and Maintenance

In this webinar, PESTECH will describe their transition to intelligent substation design and its ...

High Availability Networks. Application of IEC6439-3 Protocols for IEC61850 Process Bus implementation

Networks can now be built for the first time with genuinely uninterrupted data communication betw...

Understanding Moisture Dynamics in Power Transformers

While the need to measure moisture in power transformers has been well documented and is universa...

Regional Market Outlook for the WECC and ERCOT

Looking for an independent market outlook and analysis of the WECC and ERCOT power markets? ...

Streamline Utility Field Inspections to Improve System Reliability &  Customer Satisfaction

Arm your workers with solutions that improve productivity and customer satisfaction. Listen in an...

EL&P BUYER'S GUIDE PRODUCTS

MITEM Corp

Provides CRM solutions for regulated U.S. public utilities. The product, MitemView integrates differently designed systems to share critical data a...

Resources on Demand

Manages resource requests, tracks personnel movements, and supports lodging/logistics during a power restoration event.

Smart Grids

Quanta is contributing to its customers' smart grid initiatives by installing technology on power networks to provide energy management solutions f...

Horizontal Directional Drilling

With 28 small, mid-sized and large drilling rigs, Quanta Pipeline Services is one of the largest horizontal directional contractors in the world fo...

FEATURED ENERGY JOBS

View more Job Listings >>

POWERGRID International

April 2014
Volume 19, Issue 4
1404pg-cover

ELECTRIC LIGHT & POWER

January 2014
cover