Tres Amigas, Broadview Energy to interconnect up to 500 MW

Sponsored by

Tres Amigas and Broadview Energy announced the execution of agreements that would facilitate the development and construction of up to 500 MW of wind power in northeast New Mexico.

This agreement will enable Broadview, Tres Amigas’ first customer, to deliver its high-quality New Mexico wind power for the next 25 years to California starting by year-end 2015 and also enables the project to use the additional services to be offered by Tres Amigas when the Super Station becomes operational.

Broadview has been in development since 2011 with National Renewable Solutions (NRS) as its manager and developer. Broadview’s 12-wind turbine first phase named Brahms Wind is located five miles south of Grady, N.M. The second phase is on about 39,000 acres north and east of the Brahms Wind project. The agreements executed with Tres Amigas are integral to the viability of this much larger second phase, which is named Broadview Energy KW.

The construction value to the local economy is about $1.2 billion for Tres Amigas and over $550 million for Broadview’s wind farm. The project plans to install over 200 GE wind turbines in its footprint and is working with Mortenson Construction as its contractor. The Broadview Energy KW project is expected to create upwards of 200 construction jobs and an estimated 20 full-time, permanent jobs once construction is complete.

The Tres Amigas project will require both short- and long-term jobs in construction maintenance, scientific research, clean energy technologies and many permanent positions at its Albuquerque headquarters. It will incentivize new energy providers throughout the country to commit to new construction by providing a nationwide marketplace for the energy they produce.

Power from the wind farm is expected to be delivered over its interconnection with Tres Amigas by December 2015.

Sponsored by

CURRENT ARTICLES

Power demand records continue, ERCOT asks for conservation

07/30/2015 Electric demand this week has reached three consecutive July records, breaking 67,000 MW for the first time since 2011 

IPL to stop burning coal at Harding Street Station Unit No. 7

07/30/2015

IPL also received approval to install and operate wastewater treatment technologies at Harding Street

Hopes rise for offshore wind as U.S. builds its first offshore wind farm

07/30/2015 U.S. Secretary of the Interior Sally Jewell said Monday that lenders, regulators and stakeholders can now see a path forwa...

SunPower buys 1.5 GW U.S. solar power plant pipeline

07/30/2015

With the acquisition, SunPower has assumed ownership of projects in varying stages of development across 11 states

Riverside, California buys renewable energy from Iberdrola

07/29/2015

Iberdrola Renewables will deliver about 101,000 MWh of firm renewable energy annually  

Texas company wants to build biggest wind farm in Massachusetts

07/29/2015

If all goes according to plan, the project would begin operating in early 2017 

Panel weighs changes to Ohio's renewable energy targets

07/29/2015

Panel weighs changes to Ohio's targets for solar, wind, other renewable energy sources

FEATURED ENERGY JOBS
View more Job Listings >>

INDUSTRY STOCKS

ON DEMAND WEBCASTS

Solar + Storage: Capturing Opportunities and Overcoming Challenges

The convergence of solar and energy storage applications is under way. The combined application o...

Storage Enters the Global Stage: What’s the value proposition for your region?

For electricity storage, the events of the last two years have shown that the skepticism around t...

How to deploy mobile forms + devices to speed up field service processes & reporting

Overcoming the pain points associated with any process is much simpler and more cost effective th...

Beyond Integration: Three Dynamics Reshaping Renewables and the Grid

In a unique industry research initiative, DNV GL gathered views from over 1,600 energy sector par...

Engaging the Small and Mid-sized Business (SMB) Marketplace

This session will outline how Duke Energy leveraged Voice of Customer insights, previous experien...

EL&P BUYER'S GUIDE PRODUCTS

Nuclear Horizontal Modular Storage (NUHOMS®)

AREVA TN’s NRC-licensed NUHOMS® system ensures the highest safety and lowest dose performance. With no tipping, tripping and sliding, you have the...

Decontamination & Decommissioning

Decommissioning strategy development, cost estimates, plant modifications; system and building decontamination; RV segmentation; large component re...

Cavitation Peening

AREVA developed its innovative solution for asset management, significantly extending the life of reactor components. Cavitation Peening is a perma...

ATRIUM™ 11 for BWR Fuel

ATRIUM™ 11 design fuel – in operation since 2012 – provides significantly lower fuel rod power levels for power uprate margins, operational flexib...

POWERGRID PRODUCT LISTINGS

EtherMate® Industrial Ethernet - IO Modules

LioN-M ProfiNet device with 16 digital I/O channels, channels can be used universally as inputs or outputs, M12 socket, ro...

TRM® 2.0 - Test Results Manager PC Analysis and Reporting

Test Results Manager 2.0 (TRM® 2.0) is an all-in-one analysis, viewer and reporting tool designed for use with NOYES fiber...

OFL280 FlexTester - Handheld OTDR

AFL's OFL280 FlexTester offers an unmatched combination of fiber test functions, ease-of-use, portability, and value.

ADSS Mini-Span® Fiber Optic Cable

AFL Mini-Span® All-Dielectric Self-Supporting (ADSS) cable is designed for outside plant aerial and duct applications in l...

POWERGRID International

May 2015
Volume 20, Issue 5
1505pg_C1

ELECTRIC LIGHT & POWER

April 2015
Volume 93, Issue 2
1503ELP_C1