Georgia Power marks milestones in Plant Vogtle nuclear plant expansion

Sponsored by

Georgia Power continues to track positive progress in the construction of the new Vogtle units 3 and 4 facility near Waynesboro, Georgia. The project, among the first new nuclear units to be built in the U.S. in three decades, has marked several milestones in 2013.

Following the placement of 7,000 cubic yards of concrete for the Unit 3 basemat in March, additional project progress this year has included:

·      Delivery of the Unit 3 reactor vessel and the Unit 4 deaerator to the site.

·      Placement of the CR10 "cradle" module in the Unit 3 nuclear island.

·      Placement of the containment vessel bottom head (CVBH).

·      Installation of rebar in the Unit 3 auxiliary building walls.

·      Placement of the Unit 4 nuclear island mudmat and installation of the Unit 4 basemat rebar.

Construction of key modules continues to progress, as does work on the cooling towers for both units, condenser pre-assembly, permanent office building construction, switchyard work and raw water intake structure preparation. In addition, activities to ensure readiness for the transition to commercial operation are underway including employing and training operational personnel, developing pre-operational and startup testing, and developing operations programs and procedures. In fact, there are currently nearly 100 licensed operator candidates in different phases of the training program with 25 of these candidates being certified on the AP1000 on-site limited scope simulator in February.

Georgia Power is the largest unit of Southern Co.

Sponsored by

CURRENT ARTICLES

Utilities, trade groups, politicians react to final form of Clean Power Plan

08/03/2015

The emissions cuts are estimated to cost $8.4 billion annually by 2030 

Who wins and loses under Obama's stricter power plant limits

08/03/2015

Power plants will have to attain an even lower level of carbon dioxide pollution to be in compliance

Final EPA Clean Power Plan seeks 32 percent CO2 cut by 2030

08/03/2015

Compliance averaging period begins in 2022 instead of 2020

Clean Power Plan requires deeper power plant emissions cuts over more time

08/03/2015

Opponents plan to sue immediately, and to ask the courts to block the rule temporarily

White House fact sheet on finalized Clean Power Plan

08/03/2015

The final Clean Power Plan sets standards to reduce carbon dioxide emissions by 32 percent  

New York to give low-cost electricity to Amazon, Bausch & Lomb

07/31/2015

The companies announced Thursday have promised to retain more than 1,600 jobs and create more than 730 new ones 

VIDEO: Wind power research now focuses on cheaper, lighter

07/31/2015

Lightweight materials are seeing greater adoption in wind turbine manufacturing as evidenced by patent trends 

FEATURED ENERGY JOBS
View more Job Listings >>

INDUSTRY STOCKS

ON DEMAND WEBCASTS

Solar + Storage: Capturing Opportunities and Overcoming Challenges

The convergence of solar and energy storage applications is under way. The combined application o...

Storage Enters the Global Stage: What’s the value proposition for your region?

For electricity storage, the events of the last two years have shown that the skepticism around t...

How to deploy mobile forms + devices to speed up field service processes & reporting

Overcoming the pain points associated with any process is much simpler and more cost effective th...

Beyond Integration: Three Dynamics Reshaping Renewables and the Grid

In a unique industry research initiative, DNV GL gathered views from over 1,600 energy sector par...

Engaging the Small and Mid-sized Business (SMB) Marketplace

This session will outline how Duke Energy leveraged Voice of Customer insights, previous experien...

EL&P BUYER'S GUIDE PRODUCTS

Decontamination & Decommissioning

Decommissioning strategy development, cost estimates, plant modifications; system and building decontamination; RV segmentation; large component re...

Cavitation Peening

AREVA developed its innovative solution for asset management, significantly extending the life of reactor components. Cavitation Peening is a perma...

Nuclear Horizontal Modular Storage (NUHOMS®)

AREVA TN’s NRC-licensed NUHOMS® system ensures the highest safety and lowest dose performance. With no tipping, tripping and sliding, you have the...

ATRIUM™ 11 for BWR Fuel

ATRIUM™ 11 design fuel – in operation since 2012 – provides significantly lower fuel rod power levels for power uprate margins, operational flexib...

POWERGRID PRODUCT LISTINGS

EtherMate® Industrial Ethernet - IO Modules

LioN-M ProfiNet device with 16 digital I/O channels, channels can be used universally as inputs or outputs, M12 socket, ro...

OFL280 FlexTester - Handheld OTDR

AFL's OFL280 FlexTester offers an unmatched combination of fiber test functions, ease-of-use, portability, and value.

ADSS Mini-Span® Fiber Optic Cable

AFL Mini-Span® All-Dielectric Self-Supporting (ADSS) cable is designed for outside plant aerial and duct applications in l...

TRM® 2.0 - Test Results Manager PC Analysis and Reporting

Test Results Manager 2.0 (TRM® 2.0) is an all-in-one analysis, viewer and reporting tool designed for use with NOYES fiber...

POWERGRID International

May 2015
Volume 20, Issue 5
1505pg_C1

ELECTRIC LIGHT & POWER

April 2015
Volume 93, Issue 2
1503ELP_C1