Northwest Stave River run-of-river hydropower project secures financing

Sponsored by

Innergex Renewable Energy Inc. closed a $72 million non-recourse construction and term project financing for the Northwest Stave River run-of-river hydroelectric project located in British Columbia, Canada.

The 17.5 MW Northwest Stave River hydroelectric project is located on Crown land, about 35 km north of Mission, British Columbia. Construction began in 2011 and commercial operation is expected to begin in the fourth quarter of 2013. Northwest Stave's average annual production is estimated to reach 61,900 MWh, enough to power about 6,000 average Canadian households.

All of the electricity it will produce will be covered by a 40-year fixed-price power purchase agreement with BC Hydro, which was obtained under that province's 2008 clean power call request for proposals and which provides for an annual adjustment to the selling price based on a portion of the consumer price index. The proceeds of the financing will be used to fund about 80 percent of the total project costs.

The $72 million construction loan will carry a fixed interest rate of 5.3 percent; upon the start of the project's commercial operation, it will convert into a 40-year term loan and the principal will begin to be amortized over a 35-year period, starting in the sixth year.

The financing has been arranged by Industrial Alliance Insurance and Financial Services Inc. as agent and lead lender, and includes Stonebridge Infrastructure Debt Fund I L.P. as lender.

Sponsored by

CURRENT ARTICLES

Justices rule against EPA power plant mercury limits

06/29/2015

The Supreme Court says that the EPA overreached.

Basin Electric wins international employer of the year award

06/29/2015 Basin Electric previously received the international award in 2005 and the Dakotas Chapter 72 Employer of the Year Award i...

Duke Energy to excavate 12 more coal ash basins in North Carolina

06/29/2015

The material would be safely reused in lined structural fills or permanently disposed in lined landfills.

Building Energy to build 2 solar photovoltaic plants in Egypt

06/29/2015 The $200 million project was awarded by the New & Renewable Energy Authority of the Ministry of Electricity & Rene...

CG bags 2 electricity networks orders in Philippines

06/29/2015 The scope of work for both projects includes design, manufacture, supply, construction and installation and commissioning ...

AEP taps Siemens to modernize HVDC system Welsh in Texas

06/29/2015 Siemens will upgrade its 20-year-old system by installing new control and protection technologies, replacing the cooling, ...

Michigan utilities work to comply with power plant pollution rule

06/26/2015 The EPA estimates costs of around $9.6 billion for power plants to install and operate equipment to remove pollutants
FEATURED ENERGY JOBS
View more Job Listings >>

INDUSTRY STOCKS

ON DEMAND WEBCASTS

Solar + Storage: Capturing Opportunities and Overcoming Challenges

The convergence of solar and energy storage applications is under way. The combined application o...

Storage Enters the Global Stage: What’s the value proposition for your region?

For electricity storage, the events of the last two years have shown that the skepticism around t...

How to deploy mobile forms + devices to speed up field service processes & reporting

Overcoming the pain points associated with any process is much simpler and more cost effective th...

Beyond Integration: Three Dynamics Reshaping Renewables and the Grid

In a unique industry research initiative, DNV GL gathered views from over 1,600 energy sector par...

Engaging the Small and Mid-sized Business (SMB) Marketplace

This session will outline how Duke Energy leveraged Voice of Customer insights, previous experien...

EL&P BUYER'S GUIDE PRODUCTS

Decontamination & Decommissioning

Decommissioning strategy development, cost estimates, plant modifications; system and building decontamination; RV segmentation; large component re...

Cavitation Peening

AREVA developed its innovative solution for asset management, significantly extending the life of reactor components. Cavitation Peening is a perma...

Nuclear Horizontal Modular Storage (NUHOMS®)

AREVA TN’s NRC-licensed NUHOMS® system ensures the highest safety and lowest dose performance. With no tipping, tripping and sliding, you have the...

ATRIUM™ 11 for BWR Fuel

ATRIUM™ 11 design fuel – in operation since 2012 – provides significantly lower fuel rod power levels for power uprate margins, operational flexib...

POWERGRID PRODUCT LISTINGS

EtherMate® Industrial Ethernet - IO Modules

LioN-M ProfiNet device with 16 digital I/O channels, channels can be used universally as inputs or outputs, M12 socket, ro...

OFL280 FlexTester - Handheld OTDR

AFL's OFL280 FlexTester offers an unmatched combination of fiber test functions, ease-of-use, portability, and value.

ADSS Mini-Span® Fiber Optic Cable

AFL Mini-Span® All-Dielectric Self-Supporting (ADSS) cable is designed for outside plant aerial and duct applications in l...

TRM® 2.0 - Test Results Manager PC Analysis and Reporting

Test Results Manager 2.0 (TRM® 2.0) is an all-in-one analysis, viewer and reporting tool designed for use with NOYES fiber...

POWERGRID International

May 2015
Volume 20, Issue 5
1505pg_C1

ELECTRIC LIGHT & POWER

April 2015
Volume 93, Issue 2
1503ELP_C1